Because the design line is limited by both the existing railway from Sichuan to Guizhou, topography and room resource, before building the mian bridge and approaching bridge close to Guiyang of new Baishatuo Yangtze River Bridge for the railway from Chongqing to Guiyang, it is necessary to build 1?26km makeshift railway near the existing bridge first, and makes trains running on the makeshift railway, then builds the new bridge, roadbed and structures on the site of the old railway. There is no more than 30m from the old railway to the makeshift railway, engineers have to work close to railway two times which is being used. The rocky cutting slopes of the old railway are precipitous and high, need to cut slopes by blasting rocks in a large area. To build the makeshift railway, the old railway cuttings and embankments will be widened, in some sections, special foundations need to be reinforced by CFG piles. This paper focuses on the right construction methods, safety and reasonable prot