登录

双语推荐:承力索

承力索用于链形接触悬挂,位于接触线的上方,通过吊弦将接触线悬挂起来。由于短路接地、主导电回路不畅、雷击、线交叉互磨、补偿装置卡滞及腐蚀等原因,常出现承力索断股、断线的现象。文章以高速铁路上常用的JTMH-120承力索为例,利用数理解析对工程速算法得出的JTMH-120承力索的最大断股数进行校验,进而验证利用工程速算法得出的接触网中常用的9类承力索最大断股数的数据是有效的。依靠所得数据,参照原铁道部关于承力索补强的技术标准,结合运营维护经验,综合多年普速铁路承力索的断股补强、重接案例,提出了一种维修措施处理高速铁路承力索断5股以上的情况。该措施在管内线路上运用,取得了良好的效果。这种维修措施补充已有的承力索断股维修措施,为接触网的检修工作提供有益的指导。
The catenary cable is nsed for system with catenary suspensim. It is above the contact wire and hang it through a hanger. Because of short circuit in grounding, poor return current, lightning and wearing of strands, the breaking of catenary cables occur now and then. Taking JTMH-120 for example, the method of mathematical analysis is used to check the maximum broken quantity of catenary cables which was calculated by engineering simplified. And then, the data of the maximum broken quantity of nine categories catenary cables using engineering simplified caculation is valid. Based on the data,MOR’s technical standards have been studied, the experience of operation and maintenance and the case of catenary reinforcement in railway have been referred. The maintenance is proposed when catenary has been found damaged in high-speed railways. This maintenance has achieved good results in managed railway. The existing catenary maintenance measures are completed to provide useful guida

[ 可能符合您检索需要的词汇 ]

本文阐述了时速160公里电气化铁路单线隧道内接触网采用旋转全腕臂悬挂时(由于净空受限关节处腕臂采用对侧抬头安装),承力索座安装在两种不同状态的腕臂上,在温度应发生变化时其工作状态的分析与优劣比较。接触网腕臂支持结构的变化能够引起其零部件的选型及其功能实现程度上的变化。承力索座作为接触网悬挂、固定重要零件对其工作状态的分析,有利于其功能、结构、材质、工艺及环境适应性上的优化处理,并能够使其更好的服务于接触网系统。
This article expounds the speed of 160 km of electrification railway catenary in single tunnels using the rotary bracket when suspension (due to limited clearance joints with the contralateral wrist arm up installation), carrier cable installed in two different states of wrist arm, changes in temperature stress analysis and the working state of the advantages and disadvantages compared. Catenary bracket support structure changes can cause its components selection and function realization degree of change. Carrier cable as catenary suspension, fixed important parts on the analysis of its working state, is conducive to its function, structure, material, technology and en-vironment adaptability on the optimization of the processing, and be able to make it better serve the catenary system.

[ 可能符合您检索需要的词汇 ]

吊杆损伤是中式钢管混凝土提篮拱桥的常见损伤。由于吊杆损伤对索力以及自振频率均有明显影响,所以吊杆损伤的定位以及定量分析对桥梁检测至关重要。文中以铜瓦门大桥为背景工程,在有限元基准模型的基础之上,采用弹性模量折减法计算分析典型吊杆损伤组合对全桥吊杆索力变化的影响,对获取的大量计算数据加以提炼总结,得到了对吊杆损伤评估具有参考意义的结论。
Damages-to-the-suspenders-are-common-in-half-through-CFST-X-arch-bridges.Since-the-sus-pender-damage-will-influence-the-cable-forces-and-natural-frequencies-obviously,positioning-the-dam-age-and-analyzing-the-damage-degree-are-important-for-bridge-inspection.Based-on-the-baseline-finite-element-model-of-Tongwamen-Bridge,Young''s-modulus-reduction-method-is-employed-to-simulate-the-cable-force-changes-caused-by-the-suspender-damage.Numerical-results-are-investigated-and-summa-rized,and-the-conclusions-obtained-are-meaningful-for-evaluating-the-suspender-damage-of-half-through-CFST-X-arch-bridges.
分析关节式电分相的烧伤原因,提出一种通过检测关节式分相中性区段承力索电流进行机车闯分相故障报警的方法。介绍了机车间分相远程报警装置的实现方案和软硬件工作原理,以及为解决报警装置电源供给的措施。
This paper analyzes the phase of the joint-type electric burns causes, proposes a targeted joint-style points by detecting the phase of line current to break phase of the locomotive fault alarm method. Focuses on the locomotive Chuang phase implementation of the remote alarm device programs and hardware and software works, as well as solve the alarm device power supply of a variety of measures

[ 可能符合您检索需要的词汇 ]

区别于预应锚固系统,在传统钢框架后锚梁锚固系统的基础上,南京长江第四大桥采用一种新型悬桥主缆锚固系统——分布传式锚固系统。钢框架后锚梁锚固系统依靠后锚梁刚性载,应集中明显,有一定的结构和安全风险。分布传式锚固系统锚固区域通过布置多排钢筋混凝土榫剪键(PBL),变刚性载为柔性载,索力渐次传递至锚体混凝土;变集中载为分布传载,扩大了传区域,减小应集中,降低结构风险;利用PBL良好的延性,同时通过设置末端压板,为结构整体提供足够的安全储备。本文对这种新型锚固系统的设计作了简要介绍。
Superior to conventional pre-stressed anchorage system,a new anchorage system design con-cept of cable-stayed bridge,the stress distributed transmitting anchorage system,is adopted to the Fourth Nan-jing Yangtze River Bridge referencing to the design of conventional steel framed anchorage system. The conven-tional steel framed system relies on the back anchorage beam,which provides rigid bearing supports and results in large concentrated stress,and has certain risks on both structural and safety aspects. However,the stress dis-tributed transmitting anchorage system is arranged with several rows of reinforced concrete tenon-joint shear con-nector (PBL) in anchoring area in order to transform the rigid bearing supports to flexible bearing supports which helps cable stress gradually delivering to concrete anchorage block,changes the pattern of stress distribu-tion from concentrated to distributed,enlarges the stress region,decreases the degree of stress concentration, minimizes the struct

[ 可能符合您检索需要的词汇 ]

大跨径拱桥主拱圈施工特别是缆吊装钢拱架现浇主拱圈施工是一个复杂的过程。为保证施工安全,控制施工精度,需要精确确定钢拱架裸拱线形及其吊装过程扣的控制索力。以某主跨108 m的上式钢筋混凝土拱桥为例,对缆吊装钢拱架现浇主拱圈的施工过程进行模拟,给出钢拱架裸拱线形及预抬高值的迭代算法及合理的扣索索力,对同类型桥梁仿真计算具有借鉴意义。
Construction of main arch rings of large-span arch bridges, especially construction of cast-in-situ main arch rings of cable-hoisting steel arches is a complicated process. In order to guarantee safety of construction and control precision of construction, the naked arch layout of steel arches and control cable force of pintle cables during hoisting should be accurately determined. With a deck type reinforced concrete arch bridge at 108 m main span as an example, this paper simulates the construction process of cast-in-situ main arch rings of cable-hoisting steel arches and presents iterative algorithm for naked arch layout and value of pre-raise of steel arches and reasonable force of pintle cables with a reference significance for simulation calculation of bridges of the same type.

[ 可能符合您检索需要的词汇 ]

Loukouni桥是刚果(布)1号公路Ⅱ期工程中的一座采用缆吊装的上式钢箱拱桥,为保证其施工过程的安全性,用零弯矩法、零位移法和定长扣法,分别获得了施工过程中扣索索力和拱肋预抬值,并利用通用有限元软件ANSYS的生死单元功能对施工过程进行了仿真分析.计算结果表明:定长扣法和零位移法确定的施工方案均能满足拱肋线形、施工截面应和变形控制的要求,定长扣法更优,可以作为该桥施工首选的设计方案;试算零位移法是确定施工扣索索力的一种简便有效的方法.
Loukouni bridge is a deck type arch bridge with box section and is a part of the second stage of the first national road project of the Republic of Congo. This bridge will be constructed with cable erecting equipment. To make sure its construction safety,three methods,including the zero moment method,the zero displacement method and the invariable cable method,were used to calculate the cable force of fastening cable and the pre-camber of main arch during the construction. Live and dead elements provided by the general FE (finite element)software ANSYS were utilized to simulate the construction of the bridge. The research result shows that both the zero displacement method and the invariable cable method can meet the construction demand in terms of the shape of the arch,the stress of arch section and the deformation of the arch. In the two methods,the invariable cable method is better and should be the first choice applied to the Loukouni bridge. The trial zero displacement method is a

[ 可能符合您检索需要的词汇 ]

为了为接触网覆冰的在线监测提供理论基础,对覆冰后接触网的静态响应进行研究。首先,利用ANSYS建立6跨张自动补偿的简单链型悬挂接触网的有限元模型,对不同覆冰厚度时的接触网的静态响应进行仿真分析,得到随覆冰厚度的变化的接触线和承力索的弛度变化以及下锚处位移。然后,基于相似理论建立1/50的6跨接触网小比例模型。通过模型试验得到不同厚度下接触线和承力索的下锚处位移,对比小比例模型的仿真和试验结果验证了小比例模型的可用性。将模型试验结果推广到实际接触网,对比推广后的试验结果和实际接触网的仿真结果,进一步验证了小比例模型的正确性。该小比例模型可为深入研究接触网特性试验提供试验基础。
In order to provide theoretical foundation for on-line monitoring of catenary, the static response of ice-coated catenary was investigated. First, a six-span automatic tensioned simple catenary finite element model was built via ANSYS, the static response of ice-coated catenary was conducted with different ice thicknesses, sag variations and end anchorage displacements of contact and messenger wire with different ice thickness were obtained. Then a 1/50 scale model of six-span catenary was constructed based on the similarity theory. End anchorage displacements of contact and messenger wire with diverse ice thicknesses were achieved through small-scale model test. Comparison of the displacements between small-scale model test and finite element simulation validated the feasibility of small-scale model. The results were converted to real catenary, which were compared with simulation results of real catenary, confirmed the correctness of the small-scale model. This small-scale model offer

[ 可能符合您检索需要的词汇 ]

结合沪杭客专松江特大桥136#、137#门式墩施工,介绍了上跨既有铁路的门式墩盖梁采用工字钢膺架法施工技术,论述了在紧靠既有铁路、结构底面紧邻接触网承力索情况下,盖梁现浇的主要控制要点,对上跨既有线结构现浇法施工有一定指导意义。
The paper,based on No.136 and No.137 gate pier construction of Songjiang Bridge on Shanghai-Hangzhou pas-senger railway,introduces that the construction technology of gate pier capping beam over existing railway with the “工”style beam scaffolding construction technology.And it discusses the key control points of capping beam casting close to ex-isting railway and the structure underneath close to the catenaries,which can provide reference for casting construction over existing structure.

[ 可能符合您检索需要的词汇 ]

采用计算机有限元仿真技术,建立接触线、承力索以及吊弦的有限元模型,通过合理的边界条件定义和工况定义,客观准确地反映弓网实际施工中的安装、施加预紧和剧定等的安装顺序,实际施工的安装顺序、载荷以及约束,进行反复的迭代建模,通过多次建模和计算来确定符合安装验收标准的吊弦长度;同时使仿真建立的接触网学状态符合实际情况。
This paper studied the dropper length calculation and determination by computer FEM simulation thoroughly and put forward to a iteration simulation and modeling method to determine the dropper length. This method first builds the FEM modeling of contact wire, pantograph, and dropper system, and then describe the boundary condtion and loadcases according to the actual procedures of installation, pre-loads and fixtures in real construction. By iteration simulation and modeling, the dropper length approachs to the standard of construction and the mechanical state of catenary system.

[ 可能符合您检索需要的词汇 ]